A set of operational activities 

Operational SafetyProduction accelerationProduction CostSweep efficiencyDisplacement efficiency

FlowratesInfill drillingCompletion\Lift design & integrity

Increasing

well-reservoir contact


Optimising

well-reservoir contact

(Conformance control)






New wellsSide-tracksFlow StimulationFlow Shut-offEOR


The above activities are facilitated by four execution mechanisms: 

...

Tip
iconfalse

 1. Where to drill the new well or side-track and how to complete it ?


2. Which wells to workover and how ?


3. Which wells to change the flow rate and whether increase or decrease ?


4. What fluid and at what time to inject ?


6. If Is there is a bottle neck bottleneck in surface infrastructure and whether it needs update ?

...