Pressure transient survey in producer during the pressure fall period caused by opening well for production or increasing its production rate

 (see Fig. 1):.


Image Modified

Fig 1. Drawdown

starting after well is closed at 3,600 hrs and going through pressure recovering for 7 days

pressure decline (blue dots)

.The grey dash line shows bottom hole pressure history before 3,600 hrs in case it would have been recorded

for 2,300 hrs after opening the well for production at 100 m3/d.



Interpretation

...

Interpretation of DD is based on:

 

  • records (see Fig. 2)



Image Added

Image Added

Fig. 1PTA Diagnostic Plot for vertical well in single-layer homogeneous reservoir with impermeable circle boundary (PSS).

Gauge pressure is in blue and log-derivative is in red.

Fig. 2Pressure diffusion model fitting to pressure gauge data.

Gauge pressure is in blue and log-derivative is in red.