One of the efficiency metrics of Financial Investment defined as:

LaTeX Math Block
alignmentleft
\mbox{PI} = 1 + \frac{\mbox{NPV}}{\mbox{I}_0}

where

LaTeX Math Inline
body--uriencoded--\mbox%7BNPV%7D

Net Present Value

LaTeX Math Inline
body--uriencoded--\mbox%7BI%7D_0

Initial Investment


The key difference with NPV is that PI shows a value of returns per unit cash invested

This particularly means that some projects with higher NPV may be less attractive in PI terms than lesser NPV projects as they require a high initial investment.

This allows a fair comparison of investment efficiency between two investment projects with different initial investments volumes.


The corporate investment policy usually dictates that:

  • investment Projects with PI ≤ 1 should be rejected

  • investment Projects with higher PI should have a priority over the projects with lower PI

  • investment Projects with lower PI are added up to the Investment Package to reach the pre-set value of affordable Initial Investment (I0)

  • investment Projects with lower risk should have a priority over the projects with higher risk


The quantification of Project's is performed individually for each Project based on its nature.


Weighing the Project's risks against PI to include to or exclude from  Investment Package is based on the Corporate Investment Policy.