Page tree

A specific study in Petroleum Production with a focus on prioritising production development and maintenance procedures based on their expected NPV / PI value.

In its simple form it can be thought as a spreadsheet with production development and maintenance procedures sorted out by a simple descending filter so that highest NPV / PI values are at the top of the list.


Investment Period = 5 years


FacilityActionBudget, M$NPV, M$PI, %
1Oil producer W-12Drilling1.00.880%
2Water Injector W-04Water shut-off 0.30.260%
3Oil producer W-03Rate Optimisation0.20.2100%
4Oil producer W-12Bullhead Acidizing0.030.1333 %
5Booster Pump BP-12Installation


6Oil producer W-09Pressure Testing0.01
7Water Injector W-04Production Logging0.05


Depending on application (long-term MDP, short-term FDP, routine WRM etc) the Investment Planning metrics and workflow may vary and selection of production development and maintenance procedures is normally based on either:

  • Fixed investment budget

  • NPV threshold

  • PI threshold



See Also


Petroleum Industry / Upstream /  Production 

Field Development Planning ] [ Well & Reservoir Management ]